Priority Fill Panel – FPA 19
Go Back
Operation
 

Cascade

zoom

The Priority Fill Panel distributes compressor discharge gas firstly to the forecourt, secondly to cascade high bank, thirdly to cascade medium bank, fourthly to cascade low bank. The ¾” high flow tube work/EIS valve arrangement included on this panel design is part of cascade to forecourt decant lines. Connections are ¾” to ensure the panel can be used for VFF of large buses (e.g. 200 m3/fill).

Performance

 
Compressor disch. to Cascade/Forecourt Cv 2.5 (4000 Sm3/hr) Sketch Priority Panel
Cascade to forecourt Cv 6.16 (10000 Sm3/hr)
Installation Guide  

This combination isolation priority panel is easily installed.

Inlet ½” OD Stainless Steel Tube
Outlet 3 x ¾” OD Stainless Steel Tube to Cascades
3 x ¾” OD Stainless Steel Tube to Dispenser
Air Connection ¼” Line
Electric Connection 1 ph 220V to solenoid valve
Operating Temp -40oC to +60oC
 

Service Characteristics

Simple onsite adjustment to pressure setting by allen key (hexagon wrench) for alteration of spring pressures on priority valves. Recommended annual replacement of priority valve seals.
   
Approvals and Ratings

 

Design Standard ISO 9001
Design Codes

NZS 5425, AG 504, NFPA 52

Test Pressure 3600psi   250 bar
Proof Pressure 4000psi            275 bar
Sequence Pressure

3200psi (normal setting)

Materials

 
Fittings

Parker Zinc Plated

Frame Zinc plated steel gear plate

Principle Components - Features & Benefits

  1. Proven reliable Intermech spring loaded 3/8” Priority Valve features special spring design to achieve excellent “memory”. Consistent sequencing between cascade banks it crucial to achieving station energy efficiency & reducing NGV fill times

  2. Proven “non-jamming” Intermech ½” non-return Valve incorporates cleanable SS mesh filters

  3. Elimination of electrics – simplifies station fault diagnosis and maintenance

  4. Pre-piping of cascade to forecourt decant emergency isolation system simplifies installation

  5. Isolation valves are full bore ensuring minimal pressure drop through panel thereby facilitating VFF
 
 
 